One Cape Town Roof Now Powers Two Malls and an Office Park

Redefine's R106m solar plant wheels power over Cape Town's grid to three of its properties, three years after it was announced and R20m over budget.

Aerial view of the Massmart distribution centre in Brackengate, Cape Town, its roof covered in solar panels
Image: TechCentral

[ The short version ]

  1. 01Redefine Properties has switched on a 7MWp, R106m solar plant on a warehouse roof in Brackengate, Cape Town.
  2. 02The power is wheeled over the City of Cape Town's network to Kenilworth Centre, Blue Route Mall and The Towers office precinct under a 20-year commitment.
  3. 03It is expected to produce 9.89GWh a year, more than three times what the city's pooled wheeling programme had moved by September.

A warehouse roof in Cape Town is now feeding two shopping centres and an office park across the city. Redefine Properties has switched on a R106-million solar plant on the roof of the Massmart distribution centre in Brackengate, TechCentral reported on 23 October.

The plant is rated at 7MWp and is expected to generate 9.89GWh a year. Its electricity is wheeled, or carried, over the City of Cape Town's network to Kenilworth Centre, Blue Route Mall and The Towers office precinct, under a 20-year commitment. The city's pooled wheeling programme had moved about 3.1GWh by September, according to TechCentral, so this one plant will produce more than three times that in a year.

10GWh
Expected annual output of Redefine's Brackengate rooftop plantTechCentral

Late and over the first estimate

  • Announced in September 2023 as a 5.5MWp system costing about R86 million, to be built in 2024
  • Redesigned to 6.2MW in August 2024, with the grid connection moved to another substation
  • Commissioning was then targeted for the fourth quarter of 2025
  • Switched on in October 2026, about R20 million above the first estimate, though with about 28% more capacity

TechCentral calculates that the cost per peak watt barely moved, from about R15.60 to about R15.10. The plant uses 11,691 panels over roughly 57,000 square metres of roof and about 300km of cabling.

"It reflects the level of engineering and coordination required to make wheeling viable at scale," said Leon Kok, Redefine's chief operating officer.

Why it matters

Wheeling lets a company generate power where it has space and use it where it needs it. For South African landlords with scattered buildings, that is a way to cut reliance on the grid without solar panels on every roof. The city plans to open pooled wheeling to the wider market "in the months ahead, if all goes to plan", mayoral committee member Xanthea Limberg said in September. Redefine has not said what share of the three properties' power the plant will cover or how much it expects to save.